Cement carrier Molvik

The Molvik is the first cement tanker to be equipped with a complete electrical installation by Piet Brouwer Elektrotechniek. It is also the first Lovik cement installation carried out by Piet Brouwer.

Work carried out.

  • Design, delivery, and commissioning of the complete electrical installation.
  • Development and integration of an advanced bow and stern thruster control system.
  • Automatic control and protection based on the available on-board power.
  • Optimization of power distribution for reliable maneuverability under all conditions.

The Molvik was successfully delivered and meets all the client’s functional and technical requirements.

For Eureka, this was the first ship delivered by Piet Brouwer Elektrotechniek; five follow-up ships have since been commissioned.

OpdrachtgeverEureka
ShipyardRoyal Bodewes
Delivery2024 / 2025
Type of shipCement carrier (dry bulk / mini-bulker)
DimensionsLength 90 m, width 13 m