To reduce their CO2 emissions, Habesha decided to replace an oil-fired boiler with a 10MW electric boiler. The grid connection had to be upgraded, and a new power supply had to be installed to power both the brewery and the new boiler.
We delivered:
- New mains distribution panel 33kV
- Step down transformer 33kV->11kV, 10MVA
- Integration between the high voltage installation and the boiler controls.
- All installation materials needed
- Packing and transport
- Turn key installation